Magnet Pub - Park Royal

Magnet Pub - Park Royal

FAÇADE RETENTION, SOFT STRIP, DEMOLITION, SITE CLEARANCE,TEMP WORKS & ASBESTOS REMOVAL – PARK ROYAL

CLIENT -  RGB GROUP
LOCATION  -  LONDON
COST  CIRCA - £88,000

CLIENT - RGB GROUP       LOCATION  -  LONDON      COST CIRCA - £88,000

FAÇADE RETENTION, SOFT STRIP, DEMOLITION, SITE CLEARANCE,TEMP WORKS & ASBESTOS REMOVAL

IMG_1581

Aspect Four Demolition Services were contracted by RGB group for works in Park Royal at the former Magnet Pub.

The site was in an area that provided a challenge with the limited space available to maneuver the machinery and equipment. This had an added impact on additional works on the site covering groundworks and pilling, making coordination between our personnel and contractors crucial to the success of the project.

20180823_144940

Overview

The property itself had a large basement that extended beyond the building structure, a high reach excavator was employed beyond the basement location in order to safely carry out the removal of the top two levels of the building.

For the façade we erected extra temporary steel works to ensure it remained stable and undamaged from the demolition works.

The roof needed to be manually removed, extra care was required as the structure of the roof was connected to both the façade and the party wall next door.

 

Due to the location of the property acute care and attention was needed due to the proximity of the residential occupants next door, with service feeds running from the building to theirs we needed to
ensure that all connections remained undisturbed and intact.

Noise, dust and vibration monitoring were maintained throughout the works to ensure minimal impact on the surrounding residents.

The roads directly surrounding the site were constantly maintained by utilising road cleaners/sweepers to ensure they were kept clean for other road users and residents.

Quality Service

We pride ourselves on safe, competent and quality workmanship for all of our projects.

Health & Safety

Aspect Four Demolition is committed to going above and beyond the government standard of health and safety.

Completed - On Time

The whole project was completed on time to the agreed contract terms and to the satisfaction of the clients.